Berlin Commercial Projects Create New Space Options for Businesses
Developments in several districts are adding industrial, office and mixed-use floorspace with defined completion dates.
How we reported this

Planning for a state-owned industrial park on Bornitzstraße in Lichtenberg is scheduled to begin in 2026 on a 12,000-square-metre site intended to offer low-cost commercial rents to start-ups and craft businesses.
Industrial and Logistics Expansions Near Key Transport Links
SEGRO has completed a 27,500-square-metre expansion of its light industrial and urban logistics park near Berlin Airport. Seven units were already leased by 2025, with full completion set for August 2026. The project adds capacity in a location close to airport infrastructure that supports logistics and light manufacturing operations.
High-Rise Office and Mixed-Use Schemes in Central Districts
Real estate group Covivio has unveiled the 030BLN 130-metre skyscraper at Alexanderplatz, with completion targeted for the second half of 2027. Nearby, The Berlinian 146-metre office tower reached its topping-out ceremony in January 2026 and is due for completion in May 2027. At Südkreuz, STRABAG subsidiary ZÜBLIN has been appointed general contractor for the 75,000-square-metre sustainable mixed-use quarter B’Ella Berlin, which will combine residential units, offices and commercial spaces with completion targeted after 2026.
A separate scheme, AVIÈR, is under way near KaDeWe in City West and will deliver 4,800 square metres of office and commercial space across eight floors, scheduled for the second quarter of 2027.
Practical Considerations for Businesses
Companies seeking premises can track the staggered completion dates across these projects to align relocation or expansion plans with available supply. The range of locations-from Lichtenberg’s planned low-cost industrial site to airport-adjacent logistics units and central high-rise offices-provides options differentiated by use type, rent profile and proximity to transport infrastructure. Monitoring public announcements from the listed developers and the city administration will indicate when leasing processes open for each scheme.